Consideration for the Rejection of the Mt. Lebanon Public Safety Building Boiler Replacement Project
Passed · Tuesday, March 25, 2025
What changed
- Spending approved
$190,000
The local government has decided to reject a $190,000 project to replace the boiler at the Mt. Lebanon Public Safety Building, which means the building's heating system will not be upgraded.
Vote: Passed 4-0
Source
https://mtlebanon.org/wp-content/uploads/2025/04/CM-03252025M.pdfThe official document is the source of truth.
How the Commission voted
- Andrew FlynnmovedYea
- Craig GrellaYea
- Jeff SieglersecondedYea
- Steve SilvermanYea
Decided at: Commission Meeting — March 25, 2025